Estfeed Datahub FAQ

Here you will find answers to the most frequently asked questions about the Estfeed Datahub.

General

What is Estfeed Datahub?

Estfeed Datahub is a data exchange platform for the electricity and gas markets, ensuring efficient data exchange and equal treatment of market participants. In short, it is a platform where grid operators submit consumption and production data, and authorized parties can access that data through the platform.

Estfeed Datahub will be used in the electricity market from 22.11.2024 and in the gas market from 17.11.2026.

How can I access Estfeed Datahub as a market participant?

Energy companies with a legal basis may apply for access to Estfeed Datahub. For information on different roles, see here. To request access, please fill in the contract template and return it unsigned.

Processing your application may take up to 10 business days. Once the contract has been signed by both parties, access rights will be granted to the administrator specified in the contract. Before accessing the system, please review the network code for electricity market operation, or in the case of the gas market, the network code for gas market operation. Estfeed Datahub user manuals and additional information are available on GitHub.

Contract templates for electricity market participants:
AVP usage contract for market participants
AVP usage contract general terms

Contract templates for gas market participants:
AVP usage contract (gas)
AVP usage contract general terms (gas)

How can I get Datahub access as an energy service provider?

The energy service provider role is available only in the electricity market. Energy service providers cannot join Estfeed Datahub in the gas market.

Before joining, please review the 'For Energy Service Providers' section and its FAQ.

An energy service provider can access data only with the customer's authorization granted in the Estfeed customer portal and only via API.

Steps to onboard:

  1. Complete the application form and send it to datahub@elering.ee. We will then review your application, including an evaluation of your service purpose and personal data processing terms.
  2. Once your application is approved, fill out the Estfeed Datahub usage contract and send it to us unsigned. The purpose stated in the contract must be simple and unambiguous.
  3. We will send you your completed contract and the general terms for signing.
  4. After signing the contract, we will connect you to Estfeed. For this, we may request additional information, such as your logo for the website.

Contract templates for energy service providers:
AVP usage contract for energy services
AVP usage contract general terms for energy services

How can I access the test environment?

A Public-test environment for integration testing is available at https://public-test-datahub.elering.ee. To gain access to the test environment, please send a pre-filled test environment contract unsigned to datahub@elering.ee.

To enter into a test environment contract, you must first have an Estfeed Datahub usage contract (for the live environment).

Contract templates can be found here: electricity, gas.

Where can I find the web interface user guide?

All our guides are available in GitHub, including a dedicated user interface guide.

The guide explains step by step how to add, search for, and modify data.

Usage of the web interface is also demonstrated in the video "Estfeed Datahub Web Interface Demo". The video description includes timestamps you can use to navigate directly to topics of interest.

How can I integrate with the API?

All necessary information for API integration is available in our GitHub documentation. To get started, review the chapter on Authentication and Authorization. Message specifications are available in Swagger, and API versions and migration deadlines are available on the API Versions page.

To integrate with the API, the contractual administrator must have access to the web interface to create a technical user. You can test your integration in the Public-test environment before going live (see the question "How can I access the test environment?").

We also recommend joining the Estfeed Datahub IT working group Teams channel and meetings. To join, please email datahub@elering.ee.

Why do I see only an error message after logging in?

Access to Estfeed Datahub is available only to the administrator specified in the contract and to users added by them. Please check the following:

  • Has your company signed the Estfeed Datahub (DEP) usage contract?
  • Has the administrator or another user with admin rights added you as a user? Users are added in the web interface on the 'Users and Permissions' page.

If the problem persists, contact datahub@elering.ee.

How can I view my contracts?

Market participants can view contracts where they are a metering point owner, service provider (e.g. open supplier) or client, as well as contracts to which a client has given access via the client portal.

In the web interface:

  1. Open the 'Contracts' page.
  2. Search for the correct contract using filters. If you leave all fields blank, all contracts will be found.
  3. After pressing the 'Search' button, you can export contracts to Excel with the 'Download' button. You can export up to 40,000 contracts into Excel. For more, use more specific filters or the API.

Via API: contract search GET /api/v2/agreements, export GET /api/v2/agreements/export. For details, see the GitHub documentation.

How do I terminate the Datahub usage contract?

To terminate your Datahub usage contract, please submit a free-form application stating your wish to terminate and the desired termination date. The application must be signed by an authorized representative of your company and sent to datahub@elering.ee.

Additionally, the account administrator must terminate network contracts and close metering points in Datahub.

To terminate a network contract:

  1. Open the 'Contracts' page and locate the network contract.
  2. Click the 'Edit' button at the end of the row.
  3. Add an end date to the 'Valid until' field and click 'Save'.

To close a metering point:

  1. Open the 'Metering Points' page and find the required metering point.
  2. Click the pencil icon at the end of the row. If not visible, scroll right using the horizontal scrollbar above the table.
  3. Change the connection status to 'Disconnected'.
  4. Check that all fields marked with an asterisk (*) are completed. If any are empty, changes will not be saved. Fill in the missing fields before saving.
  5. Click 'Edit'.

After these actions, we can terminate the AVP contract and close the account in Datahub.

For Grid Operators and Other Metering Data Submitters

How can I add metering points?

Each grid operator, line owner, closed distribution network operator, aggregator, producer, gas station, and charging point operator has its own EIC code range assigned by Elering. A market participant may register metering points only with an EIC code within that range.

Therefore, before creating a metering point, make sure you have selected the correct role in the web interface. The required fields vary by role: for example, as an aggregator, you must add a higher-level metering point EIC code, while in other roles the transmission network EIC code is required. Once registered, the metering point type cannot be changed.

Registering a metering point in the web interface:

  1. If you do not know the next available EIC code, generate it in Datahub:
    Open 'Metering Points' → 'Metering Points Bulk Upload' and click 'Generate EIC Codes'. In the 'Quantity' field enter the desired number of EIC codes and click 'Generate'. Copy the displayed EIC code(s) and enter it/them in the 'Metering Point EIC Code' field in the next step.
  2. Open the 'Metering Points' page and click 'New'. Fill in at least all fields marked with an asterisk, make sure the data is correct, and click 'Create'.
    For the 'Transmission Network EIC' field, add the Elering substation EIC code. If you do not know the correct code, you can temporarily use 38A-1234567890-1 and replace it with the correct one later (see the next question "What is the transmission network EIC code?"). As an aggregator, add the higher-level metering point EIC code instead.
  3. Before sending metering data, link a network contract to the metering point: 'Contracts' → 'New contract'.

To add multiple metering points at once, use the 'Metering Points Bulk Upload' page: download the template file, fill it, and import the completed file.

Illustrated guide: GitHub documentation.

Registering a metering point via API:

  1. Get the next available EIC code with POST /api/v1/eic/amount
  2. Add the metering point with POST /api/v2/meter and verify data is correct
  3. Before sending metering data, link a network contract to the metering point

For more detail, see the GitHub documentation.

What is the transmission network EIC code?

The transmission network EIC code field must be filled with the substation EIC code. Substation EIC codes are available here.

If you do not know the correct substation EIC code, you may temporarily use 38A-1234567890-1, but this should be replaced with the correct code later.

How can I change metering point technical data?

According to the electricity market operation network code, grid operators must ensure that data submitted to Estfeed Datahub is correct, up to date, and enables proper settlements and data exchange. Address information in particular should be properly formatted and error-free. To check addresses, we recommend using the public service of the Land Board: https://xgis.maaamet.ee/adsavalik/.

Updating data in the web interface:

  1. Open the 'Metering Points' page.
  2. Click 'Search' or fill in a filter field. It is not necessary to fill all fields.
  3. At the end of the row is a pencil icon that opens the edit window. If not visible, scroll right using the horizontal scrollbar above the table.
  4. Make the necessary changes and click 'Edit'.

To make changes via API:

Use PUT /api/v2/meter. For details, see GitHub.

The metering point type cannot be changed. For example, a border metering point cannot be changed into a regular one: in such cases, generate a new EIC code and register a new metering point.

How can I view border metering points?

Border metering points can be viewed in the web interface on the 'Border Metering Points' page or via the API service POST /api/v1/meter/search/border. Border metering point data can be queried in the main metering data search (on the 'Metering Data' page) by EIC code and period.

How often must I submit metering data to Datahub?

In the electricity market:

  • Preliminary metering data for the previous day by 10:00 on every business day;
  • Final metering data for the previous calendar month by the 5th of the following month.

In the gas market:

  • Preliminary metering data for the previous day by 13:00 on every business day;
  • Final metering data for the previous calendar month by the 7th of the following month.
How can I add metering data?

Metering data can be added in the web interface using an Excel file or via the API. The metering point must first be registered in Datahub and have a network contract.

Adding metering data in the web interface (step-by-step guide with illustrations in GitHub):

  1. Open the 'Metering Data' page and click 'Template'. Choose the start and end dates and click 'Download'. For electricity, the template is automatically created with 15-minute periods—times are not entered manually. For gas, also choose the resolution (1 hour or 1 day).
  2. Enter the metering point EIC code on each row and fill in the quantities. The file may contain data for multiple metering points. For bidirectional electricity metering points, also fill in the net quantity columns (NET IN and NET OUT). Do not change the template format, dates, or times. Detailed guide: Adding metering data via Excel.
  3. On the 'Metering Data' page, click 'Import', select the completed file, and click 'Import' again.
  4. If there were no errors in the file, data processing will begin. Starting processing does not mean data has been saved yet.
  5. Check the processing result: click 'View processing result' in the pop-up, or open 'Metering Data' → 'Metering Data Status'. Data submitters must monitor processing status.

Adding metering data via API:

  • Electricity metering data: POST /api/v2/metering-data/electricity;
  • Gas metering data: POST /api/v2/metering-data/natural-gas;
  • Processing status: GET /api/v2/metering-data/status.

You can send up to 35,040 electricity periods or 8,760 gas periods in a single message. For bidirectional electricity metering points, net quantities must also be submitted starting 01.08.2026. Message specifications are in Swagger, more details in GitHub.

What does "Reading time" mean when adding metering data?

"Reading time" indicates when the data was obtained from the meter. If data for the same period is submitted multiple times, Datahub displays the data with the most recent Reading time.

The Excel template in the web interface no longer has a Reading time column: when uploading a file, the upload moment is used as the Reading time. When submitting via API, the rTime field is optional. If left blank, the data acceptance time is used.

Why do I get error messages when adding metering data using Excel?

Estfeed Datahub only accepts correctly filled files based on the Datahub template. If there is an error, the system shows the Excel worksheet and row number with the issue. If it is difficult to find the error, try uploading the file in smaller parts. More detailed instructions are on GitHub.

The most common issues and solutions:

  • The metering point does not belong to the market participant: check the EIC code. You may send data only for metering points you are authorized for.
  • Metering point not found: register the metering point before submitting data.
  • Missing EIC code on some rows: each row must contain the metering point EIC code.
  • Excel structure: the file must not contain blank or non-metering-data worksheets.
  • Formulas: enter values, not formulas.
  • Too many decimal places: values may have up to 3 decimal places. Extra decimals may not show in the cell, so check the cell's actual value.
  • Period start and resolution: electricity data are submitted in 15-minute periods. If your meter measures hourly, divide the hourly value by four. Do not change dates or times in the template.
  • Mandatory columns: each filled IN or OUT quantity must have a selected Reading Type (METERED or ESTIMATED).
  • Net quantities: if you fill in the NET IN column, also fill in NET OUT (and vice versa). Only one may be positive per period. Only grid operators and closed distribution network operators may report net quantities.
  • Role suitability: Only grid operators, line owners, closed distribution network operators, charging point operators, and aggregators can send metering data. If you operate in several roles, select the appropriate role at the time of submission.
Why were some metering data not saved to Datahub, but there was no error message?

Metering data is processed in order and some errors only occur at the time of saving. Acceptance of a file or message does not mean the data was saved. Therefore, always check the processing status:

  • In the web interface: 'Metering Data' → 'Metering Data Status';
  • Via API: GET /api/v2/metering-data/status.

Status can be PROCESSING (processing ongoing), SUCCESSFUL (saved), or ERROR (with errors). In an API message, a single faulty metering result causes the entire message to be assigned status ERROR. The error report is available for 7 days.

Processing may take time under heavy load. If your message does not reach a final status, assume a problem occurred and resend the data.

How can I check metering data for my metering points?

You can check metering data in the web interface on the 'Metering Data' page or via the API.

In the web interface: enter the metering point EIC code and period start (optionally also end), then click 'Search'. The results can be viewed in various resolutions, such as totals by month. To download to Excel, click 'Download' after searching. The file will contain data at its original resolution.

Via API:

  • Electricity metering data: GET /api/v2/metering-data/electricity;
  • Gas metering data: GET /api/v2/metering-data/natural-gas.

The request must specify the purpose. For your own metering points, use OWN_MP_MANAGEMENT. The v1 service POST /api/v1/meter-data/search is deprecated, will be closed on 31.01.2027, and does not provide net quantities.

You can view data for one metering point at a time, both in the web interface and via API.

Detailed instructions are in the GitHub documentation.

How can I correct metering data?

Grid operators may correct their submitted data if necessary. To do so, upload the corrected metering data to Datahub again, either using Excel or API. Metering data may be corrected up to 12 months back.

For the same period, Datahub will display the data with the most recent Reading time. For data uploaded with Excel, the Reading time is set automatically, so a new file will overwrite previous data. Via API, either leave rTime blank or set a later time than the previous data for the period.

Only correct data if you have found an error. Re-uploading data with unchanged values is not allowed if the actual metering data did not change.

Can I download all monthly metering data for my metering points at once?

Not currently. In Estfeed Datahub, you may search for and download metering data for one metering point at a time, both in the web interface and via API (GET /api/v2/metering-data/electricity).

If you require an overview of all metering points, you have two options:

  • Grid operator client report shows summary quantities (production, consumption, net quantities) and number of submitted records for each metering point for the period. It is useful for checking if all data has been submitted. For the electricity market, it is generated each month from the 1st to the 8th; for the gas market, it is generated daily from the 2nd of the month.
  • 15-minute data can be retrieved automatically via API by querying one metering point at a time.

We will inform you when downloading data for multiple metering points at once becomes possible in Datahub.

How can I add a new network contract?

A new network contract can be added in the web interface on the 'New Contract' page or via API using POST /api/v2/agreements. To add multiple contracts at once, use POST /api/v2/agreements/bulk. You will need the metering point EIC code, client EIC code, and contract validity period.

Points to note:

  • You cannot have two valid network contracts for the same metering point in the same period. To add a new one, you must first end the previous contract.
  • The metering point must be previously registered in Datahub and belong to your market participant account.
  • Network contracts can be added by grid operators, line owners, closed distribution network operators, producers, gas stations, and charging point operators. Suppliers and aggregators cannot register contracts.
How can I register a new client?

If a customer has never had a grid contract, their information is likely missing from Datahub, and the grid operator must add it. Always add the customer's personal identification code or registration code. For a foreigner without an Estonian personal identification code, the document number is sufficient.

In the web interface:

  1. Start adding a grid contract on the 'New agreement' page and add the metering point EIC code.
  2. Click 'Search customer', fill in a field (e.g. personal identification code), and click 'Search'.
  3. If the customer is found, select them. If not, click 'Register new customer' and fill in the required fields.

Via API: To search for a customer, use POST /api/v1/customer/search; to add a new customer, use POST /api/v1/customer. More info on GitHub.

Where can I find the customer's EIC code?

If a customer has ever had a grid contract, they likely have an EIC code. You can find this via customer search: start adding an agreement on the 'New agreement' page, add the metering point EIC code, click 'Search customer', and search by, for example, personal identification code. You can search for the customer via API with the POST /api/v1/customer/search service.

If the customer cannot be found, they must be registered. See the question “How can I register a new customer?”

How can I change the customer for a grid contract?

You cannot change the customer of a valid grid contract. If the customer changes, end the previous grid contract and add a new one. If the contract has not yet started, you can delete it and add the correct contract.

In the web interface:

  1. Open the 'Agreements' page.
  2. Search for the correct contract, for example by personal identification code or metering point EIC code.
  3. Click the 'Edit' button at the end of the result row.
  4. Add an end date in the 'Valid until' field and click 'Save'. The contract is now terminated.
  5. To add a new contract, click 'New agreement'.
  6. Add the metering point EIC code, customer EIC code, and contract start date.
  7. Click 'Register new agreement'. If the data are correct and the contract does not overlap with a previous one, the client at the metering point is now changed.

Via API: To amend a contract (including ending it) use PUT /api/v2/agreements/{id}, to delete a contract that has not yet started use DELETE /api/v2/agreements/{id}, to add a new contract use POST /api/v2/agreements.

How can I change customer data?

According to the Electricity Market Network Rules, the grid operator must ensure that the data submitted to Estfeed Datahub is correct, up to date, and enables correct settlement and data exchange. This also applies to customer data: the customer must be added with the correct personal identification code or registration code, or, if lacking, a document number.

The customer's name can only be changed via the API using PUT /api/v1/customer. See GitHub documentation for details.

How do I find customers on general service?

You can find customers on general service via agreement search if you filter by agreement type. A separate report is not necessary.

In the web interface:

  1. Open the 'Agreements' page.
  2. In the filter 'Agreement type', select "General service". Refine the search as needed (more options are under 'Advanced search').
  3. Click 'Search'.
  4. To download as Excel, click 'Download'. You can download up to 40,000 agreements at a time.

Via API: Use agreement search GET /api/v2/agreements with type GENERAL_SERVICE. You can also get new and ended general service periods from the data distribution service.

The Grid Operator Customer Report also shows for each metering point whether the customer is on general service (column "General service status").

Worth knowing:

  • General service agreements are technical entries created by Datahub that indicate the start and end of general service. They are not legal contracts.
  • Agreements starting in the future are not shown in the search; they will appear after they become effective.

More information: General service notification and Reports.

For Open Suppliers and Balance Providers

How can I get access to a customer's metering point and metering data for making an offer?

Under normal circumstances, access to customer data is granted by an open supply contract with the customer.

For making an offer, a customer can share access with you via the Estfeed Customer Portal. To do this, on the 'My roles and permissions' page, select 'For energy seller' and then the appropriate seller. The permission granted to the energy seller is effective immediately. This allows the open supplier to see the customer's metering point technical data, including address, and the metering data for the last 12 months.

A detailed guide for sharing permissions in the Customer Portal is available here.

If you want the customer to be able to give consent directly via your self-service, use the seamless consent sharing service. The customer is redirected to the Estfeed Customer Portal to give their consent and will then be automatically redirected back to your environment.

Permissions granted can be found with the API service POST /api/v1/customer-authorization/search or the data distribution service.

How can I access metering data?

You can view metering data:

  • in the web interface on the 'Metering data' page: enter the metering point EIC code and period, click 'Search', and to download in Excel, click 'Download';
  • via API: electricity data with GET /api/v2/metering-data/electricity, gas data with GET /api/v2/metering-data/natural-gas.

In the API request, you must indicate purpose: OPEN_SUPPLY (as open supplier), PORTFOLIO (as balance provider), or BILLING (for invoicing). The v1 service POST /api/v1/meter-data/search is obsolete, will be closed on 31.01.2027, and does not return net quantities.

You can view data for one metering point at a time, both in the web interface and via API.

You can also get notifications about new metering data from the data distribution service GET /api/v2/data-distributions/metering-data/electricity. More details are available here.

Why is metering data missing?

If you have a valid open supply agreement, you should be able to see the metering data for that period. If data for certain periods are missing, the grid operator has likely failed to submit them. Net quantities for bidirectional metering points are also submitted by the grid operator.

Please notify the grid operator or write to datahub@elering.

How can I add a new open supply agreement?

A new open supply agreement can be added in the open supplier role. In the web interface, do this on the 'Agreements' → 'New agreement' page; via API, use POST /api/v2/agreements. You will need the customer's EIC code, metering point EIC code, validity period, and information about early termination fee.

Worth knowing:

  1. The customer must have a valid grid contract at the metering point that covers the entire open supply agreement period. The open supply contract customer must be the same person as the grid contract customer.
  2. Before adding an agreement, check if there is an early termination fee requirement on the customer's current open supply agreement. If there is, inform the customer accordingly.
  3. If the customer does not have a valid open supply agreement (for example, is on general service), the contract start date must be at least 1 day in the future.
  4. If the new agreement terminates the previous open supplier agreement, its start date must be at least 14 days in the future.
  5. In the gas market, an open supply contract can only start on the first day of the month (the gas day starts at 07:00). Exception: a contract can start mid-month only if the start date matches the start date of the grid contract.
Does the previous open supplier have to terminate their agreement for me to add a new one?

No. The previous open supply agreement is terminated automatically when a new one is added. The new agreement start date must be at least 14 days in the future.

In the gas market, a new agreement can only start on the first day of the month. Thus, the start date must be the first day of a month at least 14 days in the future.

I accidentally added an agreement to the wrong metering point. What should I do?

If the agreement has not yet started, you can delete it:

  1. Open the 'Agreements' page in the web interface.
  2. Find the correct agreement.
  3. Click the 'Delete' button at the end of the row.

You can delete the agreement via API using DELETE /api/v2/agreements/{id}.

Deleting the agreement does not restore the previous seller's agreement and the customer will be left without an open supply agreement (e.g. will move to general service). We recommend notifying the previous seller about the error so they can add a new agreement if needed.

If the agreement has already gone into effect, it can be amended retroactively via agreement coordination (see the question "I forgot to add or terminate an agreement on time").

I forgot to add or terminate an agreement on time. What should I do?

For retroactive contract changes, Estfeed Datahub provides agreement coordination. The open supplier submits a change request to all affected parties. If everyone agrees, an official contract amendment is made. Only an open supplier can initiate the request and admin or contract coordination editing rights are required.

More information and instructions:

Why is data missing or incorrect in reports?

There can be several reasons for incorrect data. Most often the grid operator has failed to submit data for some metering points or there is a problem with a contract.

Worth knowing:

  • Reports only cover metering points with a valid grid contract.
  • The daily report includes data submitted by 10:00 in the electricity market and by 14:00 in the gas market. Data submitted later will be reflected in the next day's report.

To allow us to investigate the issue, mark the problematic spots in the report in yellow and send the file with a detailed description to datahub@elering.ee.

The reports' schedule and content are described on GitHub.

For Energy Service Providers

Does my service fit the energy service provider role?

An energy service provider is a legal entity that provides energy services or implements energy efficiency improvement measures in end users' devices or premises. For example, services for energy consumption analysis, energy management, or offer comparison that use customer metering data with the customer's consent may qualify for this role.

This role is only available in the electricity market. It is not possible to join as an energy service provider in the gas market.

Whether your service qualifies for the role will be determined during application review. The assessment considers, among other things, the purpose of the service, scope of data required, and compliance with data protection requirements.

To use your own data, such as in a home energy management system, you do not need to join as an energy service provider nor sign a Datahub usage agreement. An API key created in the Customer Portal is sufficient.

How to join as an energy service provider?

  1. Submit an application. Download the application form for other energy service providers (see the question “How can I get access to Datahub as an energy service provider?” in the General section), fill it in and sign it, then send it to datahub@elering.ee.
  2. Elering evaluates the application. We check whether the service fits the energy service provider role and whether personal data protection requirements are met. Elering's data protection specialist will evaluate compliance. Assessment usually takes about one week.
  3. Sign a Datahub usage agreement. After approval, fill in the contract and send it to us unsigned. We will send you a completed contract together with the terms and conditions for your signature.
  4. Integration. After signing the contract, we will register your company and grant administrator rights to the person specified in the contract. The administrator can then create a technical user for the API. We may also ask for additional information, such as your company logo.

Pay particular attention to describing the purpose of the service in the application. This description will later be published as your service introduction in the Estfeed Customer Portal under service providers. Currently published service providers can be viewed here.

Can a company registered abroad join?

You can log in to the Estfeed Datahub web interface with an Estonian ID card, Mobile-ID, or Smart-ID. Users from some countries can also log in via EU eID with their national ID, e.g. Latvian users. If logging in with your country's eID does not work, the person specified as administrator in the contract must have an Estonian personal identification code. This can be obtained, for example, through e-residency.

What must be described in the application and what are the data protection requirements?

The application must describe, among other things:

  • the service provided and the purpose for using the data;
  • whether the service is aimed at businesses, individuals, or both;
  • the types of data needed and the period required;
  • contact details of the data protection specialist or data protection contact person;
  • the company's privacy policy and terms of data processing.

The privacy notice must match the intended data processing and clearly state what purpose customer data will be used for. When selecting the data period, follow the service purpose and the principle of data minimization.

How does a customer grant me access to their data?

The customer grants permission via the Estfeed Customer Portal. Only the data owner can grant permission. For a legal entity, the right is granted by an authorised representative of the company. Consent or authorisation given outside the Customer Portal does not substitute for the access right created in the portal.

For the customer to grant permission, they must:

  1. log in to the Estfeed Customer Portal;
  2. select the role for which they wish to share data (e.g. company);
  3. open the 'My roles and permissions' menu;
  4. choose to share a permission for energy service;
  5. select your service and the metering points whose data they wish to share;
  6. set the validity period for the permission and confirm it.

A single permission can cover several metering points and sites of the same customer. The validity period can be set for a specific date, up to three years. Thus, the permission can be given for the entire duration of a one-year project and does not need to be renewed mid-term. The customer can amend or revoke a valid permission at any time.

Detailed guide for customers: Granting permission for energy service.

How do I know if a customer has granted or revoked access?

Permissions granted by the customer, the corresponding metering points’ EIC codes, and validity periods can be found with the API service POST /api/v1/customer-authorization/search. Notifications of new permissions can also be received from the data distribution service.

Since the customer can amend or revoke a permission at any time, check before retrieving data that the permission is still valid.

In the web interface, users with the 'View access rights' privilege can view received permissions.

What data can the energy service provider see?

You can retrieve the following based on the scope of access rights granted by the customer:

  • the customer's EIC code;
  • technical data of the metering point;
  • metering data: both electricity consumed from the grid and supplied to the grid, if such data has been transmitted to Datahub for the metering point.

Data about the customer's electricity contracts, invoices, package names, and price terms are not available to energy service providers.

More information: Access to data for energy service providers.

What history length, resolution, and delay are the data available with?

History. The available period depends on the access rights granted by the customer and the data need agreed in the application. If justified, you can request up to 36 months of data in the application. With a single API request, you can retrieve data for one metering point for up to 12 months.

Resolution. Electricity metering data can be retrieved with 15-minute, hourly, daily, weekly, monthly, and yearly resolution.

Data reception. Grid operators submit previous day’s metering data on each working day by 10:00. Final data for the previous calendar month are submitted by the 5th day of the next month.

Corrections. If a grid operator submits a missing measurement later or corrects a previously submitted value, the data in Datahub is updated. Corrections can be made up to 12 months back. Keep this in mind in your integration: past periods may be updated or changed afterward, so query the necessary periods regularly.

Format. The API returns data in JSON format. For each quantity there is a measurement type (METERED or ESTIMATED) and measurement time. The exact response structure is described in the metering data documentation and Swagger.

How do I integrate with the API?

After signing the Datahub usage agreement, your company administrator creates a technical user in the Datahub web interface.

Authentication. The technical user authenticates using client_id and client_secret values via OAuth 2.0 client credentials flow and receives a JWT token. The token must be included with every API request. Other required headers and identifiers are as described in the documentation. Authentication addresses and code examples are in Authentication and Authorisation.

Services:

  1. POST /api/v1/customer-authorization/search
  2. Search for customer-granted access rights, related EIC codes of metering points, and validity periods
  3. GET /api/v2/metering-data/electricity
  4. Retrieve electricity metering data per metering point

Electricity metering data can be retrieved per metering point

Energy service providers do not need to include purpose in metering data requests. Notifications about new permissions can be received from the data distribution service.

Technical documentation is on GitHub, message descriptions in Swagger.

Are joining and data retrieval subject to charges?

No. There are no charges for joining Estfeed Datahub, using the API, or retrieving data from Elering. There are no fees for joining, monthly service, customers, metering points, queries, or data volume.

Can an individual retrieve data via API for their home energy management system?

For their own metering point data, an individual can create an API key in the Estfeed Customer Portal. The API key can be created only by the owner of the metering point data (the grid contract customer); for a legal entity, by its authorised representative.

If you have been granted access rights to another person's metering point, you can view this data in the Customer Portal, but you cannot create an API key for that metering point. Therefore, that metering point will not be displayed in the API key creation selection.

Datahub API data retrieval based on granted access rights is only available to energy service providers. There is no equivalent solution for individuals or for small, independent home energy management systems.

If the data owner wants to give you API access, they can create the API key themselves and share the parameters with you at their own discretion. The key can be limited to a specific metering point and deleted at any time.

Gas Market Transition to Estfeed Datahub

When will the gas market start using Estfeed Datahub?

On 17.11.2026, the Estfeed Datahub data exchange platform will be implemented for gas market data exchange. This means that Gas AVP can no longer be used and all market participants must connect to the new system. Existing API integrations will not work in the new system. The transition to the new system is necessary to ensure the platform's reliability and sustainability. 

Where can I find additional information about the transition?

We strongly recommend that you join the mailing list, regular meetings, and Teams channel. To do so, please write to datahub@elering.ee. Documentation is available on GitHub. 

How can I test new integrations to be ready for the transition?

Testing will be possible from July 2026 at https://public-test-datahub.elering.ee/login. This environment is also used for electricity market testing.

Documentation is available on GitHub. Please read the documentation thoroughly before testing.

Access requires signing a new test environment usage agreement. 

We recommend that you review the Estfeed Datahub documentation, where all topics are described in detail.

See the Estfeed Datahub documentation.
See the web interface user guide.

Contact us at datahub@elering.ee.